Lorient plain fire seals are comprised of a sodium silicate intumescent encapsulated within a rigid PVC case, which protects the intumescent material in normal use.

In situations where seals within frames or door leaves require painting, the over painting of Lorient fire seals should not compromise the performance of the product in a fire situation. 

This assumes that the depth of paint is no greater than the guidance set out in BS 8214:2016.

Fire Seal Coating Limits

Guidance on the painting of seals can be found in BS 8214:2016 Timber – based fire door assemblies – Code of practice. Section 14 outlines the situations in which overpainting may be applied:

  • There is no evidence to suggest that overpainting of intumescent fire seals has any detrimental effect on the ability of the seals to perform efficiently.
  • However, overpainting should be avoided wherever possible, or if unavoidable should be limited to a maximum of five coats of conventional oil bound paint or varnish on the strip without damaging its effectiveness, or a maximum of 0.5 mm, whichever is the greater.

Protecting Door Frame Integrity

Damaged seals should be replaced in accordance with BS 8214:2106 section 13.2.3It is worth noting, when preparing a frame for redecorating, the use of heat or chemical strippers should be avoided if seals are incorporated. If seals are damaged by either of these processes.

They should be replaced in accordance with BS 8214:2106 section 13.2.3. It is also important not to paint over the label and plugs at the top of the door.

Can one overpaint smoke seals?

Smoke-only seals or combined fire and smoke seals should never be overpainted. It is of the utmost importance to ensure the flexible element of any smoke fin or brush is not painted as this will impede flexibility and subsequently their performance. Lorient seals are available in a range of colours, plus woodgrain so over-painting should not be necessary.

In case you missed it

WAGNER's Fire Protection Solutions At BUILDINX 2025
WAGNER's Fire Protection Solutions At BUILDINX 2025

WAGNER Group GmbH will be presenting pioneering solutions for fire protection in modern logistics properties at BUILDINX 2025 in Dortmund from November 18 to 20, 2025. The foc...

Spare A Minute For Maintenance
Spare A Minute For Maintenance

With new fire safety regulations around the corner and a renewed focus on responsible persons and coordination, Karen Trigg of Allegion UK discusses the significance of fire door h...

Fire-Dex Unveils Fire Investigation PPE For Safety
Fire-Dex Unveils Fire Investigation PPE For Safety

Fire investigators have long worked in a gray area of protection where full structural turnouts are overkill, but single-layer garments may not cover every single hazard they encou...

vfd